Principle of dry mixing mortar equipment Nov 03, 2017

Of two to about thirty thousand tons of dry mortar production line, under normal circumstances would use the 4-6 raw material tank, two of the big cans for bulk cement and fly ash, the rest of the small cans for put light calcium, coarse whiting, sand, small material, etc.

Bulk cement and fly ash can not be used for lifting equipment.

Light calcium, heavy calcium, sand and small materials need to be put into small cans using bucket elevator, and the smart material distribution system supports a bucket elevator assignment, thus avoiding waste of resources.

The metering system, with the coordination of the measurement spiral, imports the raw materials in the hopper into the measurement warehouse, and realizes the measurement of raw materials through the data feedback of the sensor.

After measuring the good material, the screw conveyor is used to guide the main bucket elevator to the mixing chamber of the mixer.

To be a pneumatic large open door, we can quickly put the mixed materials into a non-gravity mixer, and realize the continuous production of dry powder mortar.

Cement large proportion of the material can be introduced into premixed warehouse by artificial measurement after hoist, fiber, powder and other small proportion precious masterbatch can through the electronic scale metering into admixture hopper, compared with the simple type and advanced step because after the mixing machine mixing valve bag packaging machine or open bag packing machine for automatic weighing packaging.

The belt conveyor can be used to transport to the finished area.

It has the characteristics of moderate investment, short construction period and quick investment.

Equipment investment generally between 10-350 thousand, general output can reach 5-15 tons per hour.

Operation workers 3-5, equipment height 6-10 meters, floor area 20-30 square meters.